The Lab

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 3 Next »

Pre-requisite (4 weeks)

TaskMandatoryResponsible Party
Customer business contact requests connectivity through MarketFactory through product salesYCustomer
Contractual agreement and NDA signed and returnedYCustomer
Customer obtains new connectivity credentials for Trading venues to associate with WhispererYCustomer
Customer IT and Development resources allocatedYCustomer
Customer is ready to commence connectivity with testing Order management systemYCustomer
Project schedule for connectivity is confirmed with the business and Development teamYCustomer

 

Project planning (2 weeks)

TaskMandatoryResponsible Party
Meeting with customer business and development contacts to discuss trading and technical
requirements for connectivity
YCustomer / MarketFactory
Customer is sent link to Whisperer documentation and Onboarding questionnaire for
UAT & PROD
YMarketFactory
Establish any additional services required or vendor needed for integration.YCustomer

 

Gathering requirements (1 weeks)

TaskMandatoryResponsible Party
Complete and return Questionnaire by submitting results to the MarketFactory onboarding teamYCustomer
The following must be confirmed:
  • External internet source IP for UAT
  • Network Provider
  • PROD IP addresses if known
  • Confirm Development and Production site locations
  • Present trading models and behaviour e.g amends/cancels
  • Product requirements e.g instruments/currencies required from day 1
YCustomer
Follow up call with customer stakeholders to:
  • Confirm start date of the project
  • Confirm target go-live date
  • Confirm IP addresses for UAT
  • Review customer Questionnaire and trading/technical requirements
  • Review the major milestones within the onboarding process
  • Advise who the customers business contact will be for the escalation of issues
  • Answer any questions concerning connectivity with MarketFactory
  • Review contact details for the onboarding team and provide an alternate contact
YCustomer /MarketFactory

 

 

 

Note

Some venues may take a longer period of time to establish a new production connection, one such example is Thompson Reuters that can take up to 6 weeks for the establishment of a new connection, therefore this timescale must be accounted for to achieve an accurate go live date.

Customer Development and Testing (4-8 Weeks)

 

TaskRequiredResponsible Party
MarketFactory onboarding and account management to coordinate the following:
  • Allocate customer credentials for a dedicated or shared test environment
  • Raise requests for firewall changes for client source IPs
  • Configure connections within Whisperer for test sessions
  • Configure users for connectivity to UAT
YMarketFactory
MarketFactory will send customer connectivity details for UAT to the customer's development teamYMarketFactory
Customer development team test connectivityYCustomer
Customer development team integrate to the MarketFactory APIYCustomer
Integration development and QA completedYCustomer

 

Certification (1 day)

 

TaskRequiredResponsible Party
Re-confirm day 1 requirementsYCustomer/MarketFactory
MarketFactory will send the customer's development/QA team a link to the certification test packYMarketFactory
Completion of certification testsYCustomer/MarketFactory
Review and sign off on test casesYCustomer/MarketFactory

 

 

 

 

 

  • No labels