Page History
Pre-requisite (4 weeks)
| Task | RequiredMandatory | Responsible Party |
|---|---|---|
| Customer business contact requests connectivity through MarketFactory through product sales | Y | Customer |
| Contractual agreement and NDA signed and returned | Y | Customer |
| Customer obtains new connectivity credentials for Trading venues to associate with Whisperer | Y | Customer |
| Customer IT and Development resources allocated | Y | Customer |
| Customer is ready to commence connectivity with testing Order management system | Y | Customer |
| Project schedule for connectivity is confirmed with the business and Development team | Y | Customer |
...
Project planning (2 weeks)
| Task | RequiredMandatory | Responsible Party |
|---|---|---|
| Meeting with customer business and development contacts to discuss trading and technical requirements for connectivity | Y | Customer / MarketFactory |
| Customer is sent link to Whisperer documentation and Onboarding questionnaire for UAT & PROD | Y | MarketFactory |
| Establish any additional services required or vendor needed for integration. | Y | Customer |
...
Gathering requirements (1 weeks)
| Task | RequiredMandatory | Responsible Party |
|---|---|---|
| Complete and return Questionnaire by submitting results to the MarketFactory onboarding team | Y | Customer |
The following must be confirmed:
| Y | Customer |
Follow up call with customer stakeholders to:
| Y | Customer /MarketFactory |
...
| Info | ||
|---|---|---|
| ||
Some venues may take a longer period of time to establish a new production connection, one such example is Thompson Reuters that can take up to 6 weeks for the establishment of a new connection, therefore this timescale must be accounted for to achieve an accurate go live date. |
Customer Development and Testing (4-8 Weeks)
...
Overview
Content Tools